The Heavy-load Debugging of UAE SGR Project Successfully Completed
source: Author: Date: 2013-05-21 Font size: [large medium small]

On May 13, the heavy-load debugging of UAE Fujairah strategic grain reserve (SGR) project successfully completed. During the debugging process, the equipment ran normally, reached the designed rated output and completing the expected objective.

This heavy-load debugging started from April 25 and took 19 days and the heavy-load debugging and heavy-load start were mainly conducted for the loading and unload processes. During the debugging process, the project department made a reasonable arrangement and scientific planning; all the employees and participation units sincerely cooperated and made concerted efforts to overcome various dangerous circumstances, such as rainstorm, thunder and lightning, strong wind and Iran earthquake and solve various debugging difficulties and complete the debugging two days ahead of the original schedule. On May 12, the client, represented by Abdul Rahman Omar Abdulla - vice-chairman of Abu Dhabi Investment Authority, went to the project site specially, boarded on the ship loading and unloading machine to observe the heavy-load debugging of grain delivery from the storage and shipment at that time with interest, and fully affirmed the construction of SGR project and the heavy-load debugging. The Engineer and operator were also satisfied about the result of heavy-load debugging and appreciated the integration and organization capability of the project department in this process.